Analysis of Contract Change Order (CCO) Factors, Cost and Time Factors Affecting Bore Pile Work (Case Study of Cisauk Fly over Construction Project): A Systematic Literature Review

Journal Title: Engineering and Technology Journal - Year 2025, Vol 10, Issue 03

Abstract

Almost all projects, whether government or private, experience change orders requested by either the contractor or the owner. In construction projects, change orders are regulated by contract provisions, which often result in project outcomes that deviate from the initial plans. This research aims to identify and analyze the factors that cause and influence Contract Change Orders (CCOs) on the cost and schedule of bore pile work for the Cisauk flyover construction project in Tangerang Regency. The study was conducted by distributing questionnaires to respondents involved in the Cisauk flyover construction project. The research employed quantitative analysis, with data from the questionnaires processed using the IBM SPSS program. The analysis methods included validity testing, reliability testing, normality testing, and factor analysis. From the study results, the ranking of each factor will be determined, and the dominant factors influencing the occurrence of Contract Change Orders (CCOs) will be identified.

Authors and Affiliations

Indra Mahendra Sukardi , Agung W. Biantoro ,

Keywords

Related Articles

KOMBUCHA CELLULOSE GROWTH COMPARISON: UTILIZING BRANDED TEA FOR ACCELERATING ARCHITECTURAL BIOMATERIAL PRODUCTION IN INDONESIA

One of the most recent phenomenal biomaterial trends is produced by kombucha. Its cellulose becomes viral once it is experimented on as a synthetic fabric in architectural and fashion products. The uttermost issues still...

Identifying Carbon Footprint Emitted by Geodetic Engineers in San Ildefonso Bulacan When Conducting Survey Activities

Because of increasing concern about climate change and carbon emissions as a primary contributor, many companies and organizations are pursuing “carbon footprint” projects to estimate their contributions to global climat...

LETTERS EXTRACTION IN SIGN BOARD USING VARIOUS OPTIMIZATION TECHNIQUES

Accurate localization of randomly deployed sensor nodes is critically important in wireless sensor networks (WSNs) deployed for monitoring and tracking applications. The localization challenge has been posed as a multidi...

Effects of Data Breaches on Internet of Things (IoT) Devices within the Proliferation of Daily-Life Integrated Devices

IoT has revolutionized life around us very quickly. All houses, offices, and even most of the cities in turn are a blanket or mosaic figured out by inter-woven devices keeping to each other; this shows how life was final...

From Shortcut Solutions to First Principles: Addressing Challenges and Cultivating Innovation in AI Research

The rapid progress in artificial intelligence (AI) has led to an increased use of shortcut methods like distillation-based training and prompt optimization. While these approaches offer quick performance improvements, th...

Download PDF file
  • EP ID EP760383
  • DOI 10.47191/etj/v10i03.11
  • Views 16
  • Downloads 0

How To Cite

Indra Mahendra Sukardi, Agung W. Biantoro, (2025). Analysis of Contract Change Order (CCO) Factors, Cost and Time Factors Affecting Bore Pile Work (Case Study of Cisauk Fly over Construction Project): A Systematic Literature Review. Engineering and Technology Journal, 10(03), -. https://www.europub.co.uk/articles/-A-760383